IN RE: PETITION OF TENNESSEE-AMERICAN WATER COMPANY REGARDING THE 2022 INVESTMENTS AND RELATED EXPENSES UNDER THE QUALIFIED INFRASTRUCTURE INVESTMENT PROGRAM RIDER, THE ECONOMIC DEVELOPMENT INVESTMENT RIDER AND THE SAFETY AND ENVIRONMENTAL COMPLIANCE RIDER
Date Filed |
Description |
Company Filing |
02/14/2025 |
Tennessee-American Water Company Corrected Revised Tariff Sheet (Thirty-Eighth Revised Sheet No. 12 Riders-1). |
Tennessee-American Water Company |
11/26/2024 |
Consistent With The Decisions Of The Tennessee Public Utility Commission In TPUC Docket No. 18-00039, And The Commission’s Orders In Docket Nos. 24-00011 and 22-00072, Tennessee-American Water Company Is Implementing An Adjustment Of Rates To Reflect The Amortization (Normalization) Of The Protected Excess ADIT. |
Tennessee-American Water Company |
01/31/2023 |
Order Approving Petition |
Tennessee Public Utility Commission |
12/01/2022 |
Tennessee-American Water Company Excess Accumulated Deferred Income Tax (“ADIT”)
And Reconciliation Adjustment Effective January 1, 2023 Consistent With The Decisions Of The Tennessee Public Utility Commission In Dockets 18-00039 And 22-00072. |
Tennessee-American Water Company |
10/28/2022 |
Notice Of Hearing |
Tennessee Public Utility Commission |
10/26/2022 |
Letter To Chairman Herbert H. Hilliard Re: No Outstanding Procedural Matters From Melvin J. Malone, Butler Snow LLP |
Tennessee-American Water Company |
10/26/2022 |
Pre-Filed Supplemental Testimony Of Robert C. Lane |
Tennessee-American Water Company |
10/24/2022 |
Tennessee-American Water Company Response To Commission Staff Email Correspondence Filed On October 18, 2022 Re Updating Offset To Capital Recovery Riders For TCJA Excess Adit. |
Tennessee-American Water Company |
10/18/2022 |
Darlene Standley, Commission Staff Email Correspondence To Attorney Melvin Malone, Butler Snow LLP
Re: Tennessee-American Water Tariff -Updating Offset To Capital Recovery Riders For TCJA Excess ADIT. |
Tennessee Public Utility Commission |
10/18/2022 |
Pre-Filed Rebuttal Testimony Of Robert C. Lane |
Tennessee-American Water Company |
09/23/2022 |
Pre-Filed Testimony Of Robert C. Lane Adopting Pre-Filed Testimony Of Tricia N. Sinopole |
Tennessee-American Water Company |
09/19/2022 |
Direct Testimony Of David N. Dittemore |
Consumer Advocate Division |
09/07/2022 |
Tennessee-American Water Company's Supplemental Responses To First Discovery Requests Of The Consumer Advocate |
Tennessee-American Water Company |
09/06/2022 |
Order Establishing Procedural Schedule |
Tennessee Public Utility Commission |
08/30/2022 |
Tennessee-American Water Company Revised Summary of Riders Tariff Page To Reflect The Commissions Deliberations In Docket No. 22-00021, with an effective date of August 8, 2022. |
Tennessee-American Water Company |
08/23/2022 |
Order Granting The Petition To Intervene Filed By The Consumer Advocate |
Tennessee Public Utility Commission |
08/22/2022 |
Tennessee-American Water Company's Responses To First Discovery Requests Of The Consumer Advocate |
Tennessee-American Water Company |
08/17/2022 |
Letter To Chairman Herbert Hilliard Re: Tennessee-American Water Company Update To TCJA Savings Sur-Credit Ordered In Docket No. 18-00039 With New Rate Effective September 1, 2022
(With Attachments) From Melvin J. Malone Butler Snow LLP |
Tennessee-American Water Company |
08/05/2022 |
Consumer Advocate First Set Of Discovery Requests To Tennessee-American Water Company |
Consumer Advocate Division |
08/03/2022 |
Consumer Advocate Petition To Intervene |
Consumer Advocate Division |
07/22/2022 |
Consumer Advocate And Tennessee-American Water Company Joint Proposed Procedural Schedule |
Consumer Advocate Division |
07/18/2022 |
Tennessee-American Water Company Updated Summary Of Riders Tariff With An Effective Date Of August 8, 2022, Which Replaces Petitioner’s Exhibit-Proposed Tariff Sheet No. 12-Riders TNS Filed With Direct Testimony Of Tricia N. Sinopole On July 8, 2022. |
Tennessee-American Water Company |
07/08/2022 |
Direct Testimony Of Tricia N. Sinopole |
Tennessee-American Water Company |
07/08/2022 |
Direct Testimony Of Grady Stout, P.E. (With Exhibit 2022 SCEP-GS) |
Tennessee-American Water Company |
07/08/2022 |
Petition Of Tennessee-American Water Company Regarding The 2022 Investments And Related Expenses Under The Qualified Infrastructure Investment Program Rider, The Economic Development Investment Rider And The Safety And Environmental Compliance Rider |
Tennessee-American Water Company |