IN RE: APPLICATION OF ESG PIPELINE (JC), LLC FOR A CERTIFICATE OF CONVENIENCE AND NECESSITY TO OPERATE A PROCESSED METHANE GAS DISTRIBUTION SYSTEM IN JOHNSON CITY, TN
Date Filed |
Description |
Company Filing |
04/19/2006 |
Order Granting CCN. |
Tennessee Public Utility Commission |
01/05/2006 |
Notice. |
Tennessee Public Utility Commission |
12/19/2005 |
Recusal Of Director Tate. |
Tennessee Public Utility Commission |
12/13/2005 |
ESG Thanks The TRA For Its Prompt Scheduling Of The Hearing In This Matter. |
ESG Pipeline |
12/06/2005 |
Letter From The City Of Johnson City In Support Of The ESG Pipeline's Petition. |
City Of Johnson City |
12/06/2005 |
At The Hearing On December 12, 2005, Daniel Harsh Will Adopt The Pre-filed Testimony Of James Adams. |
ESG Pipeline |
12/02/2005 |
Notice Of Hearing. |
Tennessee Public Utility Commission |
12/02/2005 |
Copy Of Letter Stephen Darden Of Johnson City, Tennessee. |
ESG Pipeline |
12/01/2005 |
Letter To Chairman Jones From City Of Johnson City, Tennessee. |
City Of Johnson City, Tennessee |
12/01/2005 |
Data Response. |
ESG Pipeline |
11/30/2005 |
Data Request. |
Tennessee Public Utility Commission |
11/22/2005 |
Company Is Requesting That The TRA Convene A Hearing On The Company's Application. |
ESG Pipeline |
11/22/2005 |
Pre-filed Testimony Of James L. Adams, President Of Energy Systems Group, LLC. |
ESG Pipeline |
11/07/2005 |
Data Responses. |
ESG Pipeline |
10/14/2005 |
Data Request. |
Tennessee Public Utility Commission |
08/31/2005 |
Petition. |
ESG Pipeline (JC), LLC |